IMPLEMENTATION PLAN FOR NATIONAL PARTNERSHIP AGREEMENT
ON REMOTE SERVICE DELIVERY
BETWEEN THE COMMONWEALTH OF AUSTRALIA
AND
THE NORTHERN TERRITORY
Plan Period: 2009 - 2014
PREAMBLE
In accordance with the Terms of Reference of the Bilateral Implementation Plan, a six-monthly review of the commitments and agreed activities of this Plan ahve been undertaken to ensure the relevance and value of investment for each key activity.
The first version of the Plan covered the period August 2009 until February 2010 and is archived at: [web address]
This is the second version of the Plan and covers the full 2010 calendar year and will be referred to as the 2010 RSD NPA Implementation Plan (Northern Territory).
The Plan will be jointly reviewed annually to ensure its continuing relevance to the requirements of the Agreement and to the COAG reform agenda.
The primary machanism for implementing the commitments in this plan is the Regional Operations Centre - National Territory (ROC NT).
In addition, the Territory Government's Service Delivery Coordination Unit (SDCU), which is responsible for cross-agency implementation of the Working Future policy, will support the ROC
PRELIMINARIES
TERM OF THE IMPLEMENTATION PLAN
GOVERNANCE ARRANGEMENTS
IMPLEMENTATION
|
The Hon Malarndirri McCarthy MLA (on behalf of the Date: 06/07/2010 |
The Hon Jenny Macklin MP Date: 06/07/2010 |
| Action 1: Engagement with Communities | ||
What are we trying to do? (Purpose)
|
Commonwealth and Territory Investment: $ |
|
| What we will do (Strategies): | Who will do it? (Roles and Responsibilities) |
How long will it take? (Timeframe) |
| 1.1. Develop a community engagement and communications plan for Remote Service Delivery implementation in the Northern Territory | ||
| 1.1.1 Implement, monitor and update community engagement plans for each of the fifteen identified locations and provide reports to the BOM on their progress and effectiveness. |
ROC NT with key stakeholders |
Full implementation by April 2010 and then reports to BOM as required |
| 1.1.2 Implement, monitor and update the overarching communications strategy and provide reports to the BOM on effectiveness. | ROC NT | Commence implementation by February 2010 and then report to BOM as required |
| 1.2 Establish programs to develop community leadership and governance skills | ||
1.2.2 Provide input into the development and then implement a training program to enhance the development of leadership and governance skills for RSD sites that:
|
FaHCSIA National Office and ROC NT | Developed by March 2010 Ongoing implementation |
| 1.3 Facilitate engagement with Indigenous people and service delivery through appropriate use of interpreters | ||
| 1.3.1 Facilitated access to high quality interpreter services in each of the RSD sites (including in accordance with any national framework). | Commonwealth and Northern Territory | Ongoing |
| 1.3.2 Monitor the use of translators and interpreters through the Aboriginal Interpreter Service and where available through local collection mechanisms. | ROC NT and SDCU | Ongoing |
| 1.4 Deliver cultural competency measures | ||
| 1.4.1 Identify and meet the cultural awareness training needs of staff working in the fifteen identified locations and in the ROC NT. | FaHCSIA NO, ROC NT, with support from SDCU | Ongoing |
|
How we will know we have achieved the purpose (Performance Benchmarks):
|
||
| Action 2: Baseline mapping, service and local infrastructure audits | ||
|
What are we trying to do? (Purpose)
|
Commonwealth and Territory
|
|
| What we will do (Strategies): | Who will do it? (Roles and Responsibilities) |
How long will it take? (Timeframe) |
| 2.1 Baseline mapping | ||
|
2.1.1 Establish repeatable baseline social and economic indicators in each of the fifteen identified locations. |
FaHCSIA in consultation with SDCU | April 2010 |
| 2.1.2 Provide feedback to each of the communities on the completed baseline mapping to inform the identification of strategies and priorities for the Local Implementation Plans. | ROC NT | Upon completion of baseline mapping |
| 2.2 Building and maintaining the evidence base | ||
| 2.2.1 Develop processes and systems to ensure governments are able to effectively share and maintain data. | FaHCSIA, SDCU | Processes and systems in place by April 2010 |
| 2.2.2 Based on information contained in the baseline mapping, measure the extent of change in each of the fifteen identified locations. | FaHCSIA, SDCU | Annually |
| 2.3 Identify and prioritise service gaps | ||
| 2.3.1 Compare the standard and range of services in the RSD locations in the Northern Territory with national standards and services in communities of similar size, location and need. | FaHCSIA, SDCU and Shire Councils | Upon completion of baseline mapping |
|
2.3.2 Assess current and planned government investments and services in each of the fifteen identified locations against comparator communities and service standards. |
ROC NT, with support from SDCU and Shire Councils | By April 2010 |
| 2.4 Identify gaps in priority local infrastructure |
||
| 2.4.1 Undertake an infrastructure gap analysis across the fifteen identified locations. | FaHCSIA, SDCU and Shire Councils |
April 2010 as part of baseline mapping. |
How we will know we have achieved the purpose (Performance Benchmarks):
|
||
| Action 3: Establish integrated government planning, coordination and reporting mechanisms | ||
|
What are we trying to do? (Purpose)
|
Commonwealth and Territory
|
|
| What we will do (Strategies): | Who will do it? (Roles and Responsibilities) |
How long will it take? (Timeframe) |
| 3.1 Locationally based work | ||
| 3.1.1 Maintain and support the Single Government Interface (SGI) established in each RSD site. | ROC NT | Ongoing |
| 3.1.2 Enhance the Single Government Interface model through the effective inclusion of Shire Councils in the operation of SGI. | ROC NT and Shires | March 2010 |
| 3.1.3 Enhance local Situation Reports to effectively and accurately report on progress of Local Implementation Plans | ROC NT | Ongoing |
| 3.2 Regionally based work |
||
| 3.2.1 Maintain support from Northern Territory and Commonwealth agencies for the Regional Operations Centre (ROC) during development and implementation of Local Implementation Plans to ensure LIPs are implemented in a timely, accountable and effective manner. | Commonwealth and Northern Territory |
Ongoing |
| 3.3 Work across agreed RSD NP locations |
||
| 3.3.1 Support the work of both Coordinators-General in monitoring the implementation of the RSD NPA, including responding to recommendations of Coordinators-General sex-monthly reports. |
FaHCSIA, ROC NT and SDCU | Ongoing |
| 3.3.2 Provide secretariat support to the RSD the Board of Management. |
SDCU | Monthly |
| 3.3.3 Operate the NTG Remote Service Delivery Sub-Committee of the Chief Executives Coordination Committee. | SDCU | Monthly |
| 3.3.4 Operate the Commonwealth Government agency Remote Service Delivery Working Group. | FaHCSIA | Monthly |
| 3.3.5 Convene NGO forum established at item 15 of the preliminaries. | ROC NT | By end February 2010 |
| 3.3.6 Convene Shire Council/GBM/ROC forum to bolster and consolidate working and planning together ideals of RSD. | ROC NT | Forum date 25 March 2010 |
|
How we will know we have achieved the purpose (Performance Benchmarks):
|
||
| Action 4: Improve service design and delivery through the development of local Implementation Plans and the development of local economies and jobs for local people | ||
|
What are we trying to do? (Purpose)
|
Commonwealth and Territory
|
|
| What we will do (Strategies): | Who will do it? (Roles and Responsibilities) |
How long will it take? (Timeframe) |
| 4.1 Develop and implement Local Implementation Plans to deliver the appropriate range and level of quality services to contribute to progress against the Closing the Gap targets |
||
|
4.1.1 Develop Local Implementation Plans in each of the fifteen identified locations. The five-year Plans will include the practical goals, targets, actions, timelines, monitoring, evaluation and reporting to support the commitment to develop remote communities into well serviced townships.The results of previous planning exercises for those communities will be considered in the development of the Local Implementation Plans as will Territory-wide service delivery issues, plans, commitments and resourcing. |
ROC NT in consultation with Shire Council, Local Boards; relevant members of the communities; SDCU; Commonwealth agencies; and other stakeholders. Endorsement of each LIP by the BOM, with formal sign-off by Commonwealth, Territory Government, community and relevant Shire Council. |
June 2010 |
| 4.1.2 Implement improvements to the design and delivery of programs and services through Local Implementation Plans. | Relevant NT and Commonwealth agenciesi; Shire Councils and other stakeholders, with oversight by the ROC NT and SDCU. |
Ongoing |
| 4.1.3 Monitor progress against the Local Implementation Plans and make any necessary changes to the Plans in consultation with relevant stakeholders. | ROC NT in consultation with relevant stakeholders. | As needed, once Local Implementation Plans have been agreed |
| 4.2 Provide local Indigenous people with employment opportunities associated with investments |
||
| 4.2.1 Assess opportunities and barriers to employment in each of the fifteen identified locations. | ROC NT, SDCU and Shire Councils | April 2010 |
| 4.2.2 Build strategies and targets to address employment barriers and maximise local employment and business development opportunities. | ROC NT, SDCU and Shire Councils | By June 2010 (as part of Local Implementation Plan) |
| 4.3 Implement changes to land tenure and administration to enable development of residential and commercial properties and facilitate development of service hubs |
||
| 4.3.1 Consult with Traditional Owners, through relevant land councils, for township leasing in each of the twelve identified locations that don't yet have a township lease. Leasing arrangements should be a minimum of 40 years. Leases are in place for Nguiu, Angurugu and Umbakumba. |
FaHCSIA and SDCU | Ongoing |
|
4.3.2 Secure leasehold tenure for government infrastructure, with a view to approximating land arrangements in the fifteen locations with arrangements off Aboriginal land ot the greatest extent possible, including:
|
FaHCSIA and SDCU | Ongoing |
| 4.3.3 Review legislative and administrative arrangements and work towards a framework which allows maximum transferability of individual titles on Indigenous held land with clear and streamlined procedures, including in relation to land registration and planning related laws. | SDCU and FaHCSIA | Ongoing (to be reported upon annually) |
| 4.3.4 Negotiate with Traditional Owners for interim block lease arrangements over government infrastructure pending agreement to whole of township lease arrangements. Leasing arrangements should be for a minimum of 40 years. | FaHCSIA and SDCU | Ongoing until township leases are finalised |
|
How we will know we have achieved the purpose (Performance Benchmarks):
|
||
| Action 5: Reporting and share best practice | ||
|
What are we trying to do? (Purpose)
|
Commonwealth and Territory Investment: $
|
|
| What we will do (Strategies): | Who will do it? (Roles and Responsibilities) | How long will it take? (Timeframe) |
| 5.1 Reporting |
|
|
| 5.1.1 Provide all administrative data (as specified in Part 4 of the National Partnership Agreement and in the Implementation Plans) required for effective planning and a thorough evaluation of outcomes of the National Partnership Agreement at a national and local level. |
SDCU will coordinate collection of the required data across Northern Territory Government agencies. FaHCSIA will coordinate collection of the required data across Commonwealth Government agencies. |
To support the annual evaluation and reporting process |
| 5.1.2 Provide a report card to communities, the Commonwealth and NTG against the performance indicators, completed baseline mapping and timelines, as detailed in the Local Implementation Plans. | ROC NT, with support from SDCU and Shire Councils | August 2010 and then annually |
|
5.1.3 Report to COAG on implementation of the National Partnership Agreement on Remote Service Delivery, including:
|
FaHCSIA and SDCU | Annually each November |
| 5.1.4 Report progress against agreed goals and risks at a location level to the Board of Management. | ROC NT | Monthly, ongoing |
|
5.1.5 Provide clear statements of expenditure as allocated under the National Partnership Agreement in each location. |
Northern Territory and Commonwealth | August 2010 |
| 5.2 Continuous improvement |
||
|
5.2.1 Identify and share best practice
|
ROC NT SDCU on behalf of the NTG.
|
Ongoing |
|
How we will know we have achieved the purpose (Performance Benchmarks):
|
||
| Action 6: Risk management | ||
|
What are we trying to do? (Purpose)
|
Commonwealth and Territory
|
|
| What we will do (Strategies): | Who will do it? (Roles and Responsibilities) |
How long will it take? (Timeframe) |
| 6.1.1 Monitor and manage risks identified in the risk management plan for implementation of the Remote Service Delivery National Partnership Agreement. |
ROC NT | Ongoing |
| 6.1.2 Develop risk management plans for each of the fifteen identified locations. | ROC NT, with support from SDCU and Shire Councils | Following development of LIPS |
|
How we will know we have achieved the purpose (Performance Benchmarks):
|
||
LIST OF ACRONYMS
| BOM | Board of Management |
| COAG | Council of Australian Governments |
| DHLGRS | Department of Housing, Local Government and Regional Services |
| SDCU |
Service Delivery Coordination Unit (Part of DHLGRS) |
| EDTL |
Executive Director of Township Leasing |
| FaHCSIA |
Commonwealth Department of Families, Housing, |
| GBM | Government Business Manager |
| IEO | Indigenous Engagement Officer |
| LIP | Local Implementation Plan |
| NGO | Non-Government Organisation |
| NTG | Northern Territory Government |
| ROC | Regional Operations Centre |
| RSD | Remote Service Delivery |
| SGI | Single Government Interface |